How to carry out the Hydraulic pressure test for the boiler?« Back to Questions List
When repairs have been carried out it is customary to subject the boiler to a hydraulic test. Before testing the boiler must be prepared. All equipment and foreign matter must be removed from the water space of the boiler and the repairs have to be carefully examined.Hydraulic pressure test is carried out at 1.5 times the working pressure, applied for 30 minutes. |